This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.
Planned Development Timeline
2009-2015
- Exploration, permitting and economic study
2015
- Published pre-feasibility study
2016
- Received permits for bulk sample / advanced underground exploration
2017
- Commenced site construction
- Commenced ramp development
- Purchased x-ray ore sorting technology
2018
- Identified two high-grade gold zones
- Executed agreement for sale of gold concentrate
2019
- Renegotiated loan agreement
- Executed toll-milling agreement
- Raised C$12 MM
2019 – 2023
- Care and maintenance
- Complete bulk sample
2023
- Engage Dumas-mine restart (April)
- Engage Foraco-production mining (June)
- Gowest temporarily moved the Bradshaw mine to a “Care & Maintenance” phase (November)
2024
- Lush Land provides $10,000,000 loan.
- Advancing Phase 2 exploration surface drilling at NTGP.
- 15748593 Canada Ltd provides $10,000,000 loan.
- Acquiring Group of Gowest shareholders provides plan to take the Company private.
- Following Special Meeting of shareholders, Gowest is taken private and delisted from the TSXV Exchange.